Water Line & Services Replacement Conception Bay Highway & Long Pond Road
Georgetown, Newfoundland and Labrador
Federal contribution
$80,738
Federal share40%
of $201.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202320242025
Built
Approved 2.5 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Local Service District of Georgetown
- Construction start
- May 13, 2024(actual)
- Construction end
- Jun 3, 2024(actual)
Against the original forecast
- Construction start3 weeks earlyforecast Jun 2, 2024
- Construction end3 months earlyforecast Aug 31, 2024
Also in Georgetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65180 in the federal list. How to read these figures.