Back to projects

Bull Cove Pond

Georgetown, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$146,372
Federal share49%

of $299.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
20172018
Built
Program
Clean Water and Wastewater Fund
Construction start
Jun 26, 2017(actual)
Construction end
Apr 30, 2018(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2017
  • Construction end5 weeks earlyforecast Jun 1, 2018

Also in Georgetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47021 in the federal list. How to read these figures.