Back to projects

Resort Village of Candle Lake - Community Hall Rehabilitation

Candle Lake, Saskatchewan

completeCultureRNIS
Federal contribution
$502,654
Federal share40%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedNov 14, 2022
2023202420252026
Built

Approved 5 weeks before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Aug 1, 2024(actual)
Construction end
Nov 30, 2025(actual)

Against the original forecast

  • Construction start7 months lateforecast Jan 1, 2024
  • Construction end8 months lateforecast Mar 31, 2025

Also in Candle Lake