Resort Village of Candle Lake East Lagoon Upgrade

Candle Lake, Saskatchewan

underwayWastewaterGIS
Federal contribution
$2.6M
$2,640,000
Federal share40%

of $6.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 28, 2024
today
2024202520262027
BuiltForecast

Approved 9 months before the announcement.

Program
Green Infrastructure Stream
Construction start
Oct 22, 2025(actual)
Construction end
Dec 18, 2026(forecast)

Against the original forecast

  • Construction start7 months lateforecast Apr 1, 2025

Also in Candle Lake

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67547 in the federal list. How to read these figures.