St. Philips WWTP Treatment Expansion

Portugal Cove-St. Philip's, Newfoundland and Labrador

underwayWastewaterGIS
Federal contribution
$498,965
Federal share40%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
today
20232024202520262027
BuiltForecast

Approved 2.6 years before the announcement.

Program
Green Infrastructure Stream
Construction start
Sep 3, 2025(actual)
Construction end
Dec 10, 2026(forecast)

Also in Portugal Cove-St. Philip's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65214 in the federal list. How to read these figures.