Water Metering and Water System Upgrades

Portugal Cove-St. Philip's, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$680,126
Federal share50%

of $1.4M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017201820192020
Built
Program
Clean Water and Wastewater Fund
Construction start
Oct 2, 2018(actual)
Construction end
Sep 22, 2020(actual)

Against the original forecast

  • Construction end6 months lateforecast Mar 31, 2020