Water Metering and Water System Upgrades
Portugal Cove-St. Philip's, Newfoundland and Labrador
Federal contribution
$680,126
Federal share50%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017201820192020
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Portugal Cove-St. Philip's
- Construction start
- Oct 2, 2018(actual)
- Construction end
- Sep 22, 2020(actual)
Against the original forecast
- Construction end6 months lateforecast Mar 31, 2020
Also in Portugal Cove-St. Philip's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47000 in the federal list. How to read these figures.