Grassey Lane Water Sewer Storm Upgrades

Carbonear, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$130,584
Federal share40%

of $326.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 5, 2024
202320242025
Built

Approved 2.2 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Carbonear
Construction start
Jul 9, 2024(actual)
Construction end
Jul 9, 2025(actual)

Against the original forecast

  • Construction start6 weeks lateforecast May 30, 2024
  • Construction end6 weeks lateforecast May 30, 2025