Back to projects

Canadian Native Friendship Centre (CNFC) - 121 Street Renovation

Edmonton, Alberta

completeOtherGICB
Federal contribution
$1.2M
$1,157,435
Federal share56%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 1, 2023
20212022202320242025
Built

Approved 11 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Feb 1, 2021(actual)
Construction end
Dec 1, 2024(actual)

Against the original forecast

  • Construction start7 months earlyforecast Sep 1, 2021
  • Construction end11 months earlyforecast Oct 27, 2025

Also in Edmonton