Back to projects

Petten Building - Building Envelope Upgrade - Phase 2

St. John's, Newfoundland and Labrador

completeAdministration, Emergency and Public WorksCVRIS
Federal contribution
$1.4M
$1,412,843
Federal share71%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
202320242025
Built

Approved 2.5 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 17, 2023(actual)
Construction end
Nov 20, 2024(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Mar 7, 2023