City of Windsor - Planning - Feasibility Study and Fleet Transition Plan
Federal contribution
$116,031
Federal share80%
of $145.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedNov 26, 2024
20232024
Built
Approved 2 years before the announcement.
- Program
- Zero Emission Transit Fund
- Ultimate recipient
- City of Windsor
- Construction start
- Mar 1, 2023(actual)
- Construction end
- Sep 13, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast Oct 1, 2022
- Construction end3 months lateforecast Jun 28, 2024
Also in Windsor
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65391 in the federal list. How to read these figures.