High Street Stormwater Rehabilitation

Channel-Port aux Basques, Newfoundland and Labrador

approvedWastewaterGIS
Federal contribution
$258,798
Federal share40%

of $647.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 21, 2025
today
2023202420252026
BuiltForecast

Approved 2.5 years before the announcement.

Program
Green Infrastructure Stream
Construction start
May 4, 2026(forecast)
Construction end
Sep 30, 2026(forecast)

Also in Channel-Port aux Basques

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65414 in the federal list. How to read these figures.