Building UP! An Inclusive, Accessible & Energy Efficient Space for Families & Young Children

Windsor, Ontario

completeOtherGICB
Federal contribution
$801,248
Federal share55%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 20, 2024
202320242025
Built

Approved 15 months before the announcement.

Program
Green and Inclusive Community Buildings Program
Construction start
Mar 1, 2023(actual)
Construction end
Mar 31, 2025(actual)

Against the original forecast

  • Construction start23 months lateforecast Apr 1, 2021
  • Construction end3 months lateforecast Dec 31, 2024