Legislative Assembly Chiller Unit

Yellowknife, Northwest Territories

completeVentilationCVRIS
Federal contribution
$305,578
Federal share100%

of $305.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedDec 6, 2024
202320242025
Built

Approved 2.2 years before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 15, 2023(actual)
Construction end
Jun 15, 2023(actual)

Against the original forecast

  • Construction start6 months lateforecast Oct 3, 2022
  • Construction end2 months lateforecast Mar 31, 2023

Also in Yellowknife

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65571 in the federal list. How to read these figures.