Town of Antigonish - Bay/Main Street Municipal Servicing Upgrades

Antigonish, Nova Scotia

underwayDrinking WaterRNIS
Federal contribution
$986,400
Federal share40%

of $2.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 21, 2023
today
2023202420252026
BuiltForecast

Approved 8 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Town of Antigonish
Construction start
Oct 20, 2025(actual)
Construction end
Sep 30, 2026(forecast)

Against the original forecast

  • Construction start6 months lateforecast May 1, 2025