Transit Fleet Expansion and Electric Bus Charging Station
Charlottetown, Prince Edward Island
Federal contribution
$4.6M
$4,637,100
Federal share40%
of $11.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 2, 2023
today
202420252026202720282029
BuiltForecast
Approved 2 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of Charlottetown
- Construction start
- Mar 1, 2025(actual)
- Construction end
- Mar 31, 2029(forecast)