Back to projects

Storm Runoff Remediation and Mitigation

Petty Harbour-Maddox Cove, Newfoundland and Labrador

completeDisaster MitigationGIS
Federal contribution
$32,329
Federal share40%

of $80.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
202420252026
Built

Approved 3 years before the announcement.

Program
Green Infrastructure Stream
Construction start
Jun 10, 2024(actual)
Construction end
Jun 12, 2024(actual)

Against the original forecast

  • Construction start5 weeks lateforecast May 6, 2024
  • Construction end2 weeks lateforecast May 27, 2024