Long Run Road Water Main Replacement
Petty Harbour-Maddox Cove, Newfoundland and Labrador
Federal contribution
$89,459
Federal share50%
of $179.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2016
2017
Built
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Petty Harbour-Maddox Cove
- Construction start
- May 29, 2017(actual)
- Construction end
- Jul 31, 2017(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Aug 30, 2017
Also in Petty Harbour-Maddox Cove
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 47007 in the federal list. How to read these figures.