Long Run Road Water Main Replacement

Petty Harbour-Maddox Cove, Newfoundland and Labrador

completeDrinking WaterCWWF
Federal contribution
$89,459
Federal share50%

of $179.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2016
2017
Built
Program
Clean Water and Wastewater Fund
Construction start
May 29, 2017(actual)
Construction end
Jul 31, 2017(actual)

Against the original forecast

  • Construction end4 weeks earlyforecast Aug 30, 2017

Also in Petty Harbour-Maddox Cove