Snuneymuxw Daycare HVAC Retrofit
Federal contribution
$281,460
Federal share100%
of $281.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 1, 2023
202320242025
Built
Approved 9 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Snuneymuxw First Nation
- Construction start
- Sep 1, 2023(actual)
- Construction end
- Feb 1, 2025(actual)
Against the original forecast
- Construction start9 months lateforecast Dec 1, 2022
- Construction end22 months lateforecast Mar 30, 2023
Also in Nanaimo
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65862 in the federal list. How to read these figures.