Thornhill Community Centre - Roadmap to Net Zero
Federal contribution
$2.3M
$2,296,712
Federal share80%
of $2.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 21, 2024
2023202420252026
BuiltForecast
Approved 14 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- City of Markham
- Construction start
- Dec 2, 2024(actual)
- Construction end
- Apr 30, 2026(forecast)
Against the original forecast
- Construction start6 months lateforecast Jun 1, 2024
Also in Markham
- City of Markhams Flood Control$48.6M
- Highway 404 - High Occupancy Vehicle Lanes$46.1M
- West Thornhill Flood Control on Three Streets with Structural Sewer Replacement in the City of Markham$4.5M
- Enhancing Health and Safety at City Facilities$4.2M
- Facility Accessibility, Energy Retrofit and Emergency Operations Centre Rehabilitation$2.4M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65867 in the federal list. How to read these figures.