Back to projects

Old Days Pond Increased Access to Nature

Bonavista, Newfoundland and Labrador

approvedOtherNIF
Federal contribution
$200,000
Federal share80%

of $250.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 14, 2026
today
20252026
BuiltForecast

Approved 17 months before the announcement.

Program
Natural Infrastructure Fund
Ultimate recipient
Town of Bonavista
Construction start
May 30, 2026(forecast)
Construction end
Oct 31, 2026(forecast)

Also in Bonavista