-nlux?lux??cwix (Lower Trout Creek) Re-naturalization

Summerland, British Columbia

completeOtherNIF
Federal contribution
$559,958
Federal share62%

of $910.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 30, 2024
20242025
Built

Approved 12 months before the announcement.

Program
Natural Infrastructure Fund
Ultimate recipient
Okanagan Nation Alliance
Construction start
Jul 17, 2023(actual)
Construction end
Aug 20, 2025(actual)

Against the original forecast

  • Construction end5 months lateforecast Mar 31, 2025