Kings Transit Authority - Phase 1 - Planning Study for Electrification of Transit
Federal contribution
$100,000
Federal share40%
of $250.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 22, 2023
today
2023202420252026
BuiltForecast
Approved 9 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- Tidal Transit Authority
- Construction start
- Aug 7, 2023(actual)
- Construction end
- Sep 1, 2026(forecast)
Against the original forecast
- Construction start3 weeks lateforecast Jul 17, 2023
Also in Kings
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66437 in the federal list. How to read these figures.