Back to projects

Cube Van for Bus Shelter Maintenance (2)

St. John's, Newfoundland and Labrador

approvedPublic TransitPTIS
Federal contribution
$31,286
Federal share40%

of $78.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 28, 2023
today
20232024202520262027
BuiltForecast

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of St. John's
Construction start
Dec 1, 2026(forecast)
Construction end
Mar 31, 2027(forecast)

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66479 in the federal list. How to read these figures.