Fleet expansion with 10 hybrid/electric buses

St. John's, Newfoundland and Labrador

underwayPublic TransitPTIS
Federal contribution
$1.3M
$1,269,569
Federal share40%

of $3.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 28, 2023
today
20232024202520262027
BuiltForecast

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of St. John's
Construction start
Jul 15, 2024(actual)
Construction end
Dec 31, 2026(forecast)