Back to projects

Bus Shelter Solar Panels

St. John's, Newfoundland and Labrador

underwayPublic TransitPTIS
Federal contribution
$226,709
Federal share50%

of $453.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 18, 2023
202420252026
BuiltForecast

Approved 3 months before the announcement.

Program
Public Transit Infrastructure Stream
Ultimate recipient
City of St. John's
Construction start
Oct 6, 2023(actual)
Construction end
Mar 31, 2026(forecast)

Against the original forecast

  • Construction start8 months earlyforecast Jun 1, 2024

Also in St. John's

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66481 in the federal list. How to read these figures.