Virginia River Trail Shared User Path (Paul Reynolds to Majors Path)
St. John's, Newfoundland and Labrador
Federal contribution
$2.6M
$2,598,082
Federal share40%
of $6.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 28, 2023
today
20232024202520262027
BuiltForecast
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of St. John's
- Construction start
- Apr 14, 2023(actual)
- Construction end
- Mar 29, 2027(forecast)
Against the original forecast
- Construction start5 months earlyforecast Sep 2, 2023
Also in St. John's