Replacement of Paratransit Fleet 18 Accessible Buses
St. John's, Newfoundland and Labrador
Federal contribution
$3.3M
$3,264,605
Federal share40%
of $8.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 18, 2023
today
20242025202620272028
BuiltForecast
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of St. John's
- Construction start
- Apr 2, 2026(forecast)
- Construction end
- Dec 31, 2027(forecast)
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66486 in the federal list. How to read these figures.