8 Hybrid 40 foot buses
St. John's, Newfoundland and Labrador
Federal contribution
$3.2M
$3,230,363
Federal share40%
of $8.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 28, 2023
20232024
Built
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of St. John's
- Construction start
- Oct 31, 2024(actual)
- Construction end
- Nov 30, 2024(actual)
Against the original forecast
- Construction start2 months earlyforecast Jan 15, 2025
- Construction end3 months earlyforecast Feb 15, 2025
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66491 in the federal list. How to read these figures.