Avalon Mall Bus Shelters
St. John's, Newfoundland and Labrador
Federal contribution
$226,709
Federal share50%
of $453.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 28, 2023
today
20232024202520262027
BuiltForecast
Approved 3 months before the announcement.
- Program
- Public Transit Infrastructure Stream
- Ultimate recipient
- City of St. John's
- Construction start
- Jul 1, 2026(forecast)
- Construction end
- Dec 31, 2026(forecast)
Also in St. John's
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66496 in the federal list. How to read these figures.