Ventilation heating upgrade
Federal contribution
$160,000
Federal share80%
of $200.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 9, 2024
2024
Built
Approved 19 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux des Laurentides
- Construction start
- Aug 1, 2023(actual)
- Construction end
- Nov 1, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Jun 1, 2023
- Construction end5 months lateforecast Jun 2, 2023
Also in Saint-Eustache