Hampton Regional Multipurpose Facility 2023

Hampton, New Brunswick

completeRecreationCCRIS
Federal contribution
$8.3M
$8,300,000
Federal share40%

of $20.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20242025
Built

Approved 22 months before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Ultimate recipient
Town of Hampton
Construction start
Apr 29, 2024(actual)
Construction end
Oct 26, 2025(actual)

Against the original forecast

  • Construction end7 weeks earlyforecast Dec 15, 2025

Also in Hampton

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66749 in the federal list. How to read these figures.