Hampton Wastewater Treatment Plant Study and Upgrades
Federal contribution
$206,143
Federal share50%
of $416.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJan 20, 2017
2017201820192020
Built
Approved 5 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Hampton
- Construction start
- Apr 1, 2017(actual)
- Construction end
- May 31, 2020(actual)
Against the original forecast
- Construction start4 months lateforecast Dec 1, 2016
- Construction end4 weeks earlyforecast Jul 1, 2020