ECC - SD 38 - Hamilton Elementary, Robert Alexander Mcmath Secondary, Samuel Brighouse Elementary Ventilation Improvements

Richmond, British Columbia

completeVentilationCVRIS
Federal contribution
$377,250
Federal share80%

of $471.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 25, 2023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 15, 2023(actual)
Construction end
Nov 1, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2023
  • Construction end2 months earlyforecast Dec 31, 2023