ECC - SD 36 - Simon Cunningham Elementary Ventilation Improvements
Federal contribution
$456,016
Federal share80%
of $570.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 20, 2023
2024
Built
Approved 5 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- School District 36 - Simon Cunningham Elementary
- Construction start
- Jun 30, 2023(actual)
- Construction end
- Dec 30, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2023
- Construction end4 weeks lateforecast Dec 1, 2023
Also in Surrey
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66843 in the federal list. How to read these figures.