Schedule

Announced and approvedMay 25, 2023
2024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Mar 7, 2023(actual)
Construction end
Jul 31, 2024(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Feb 1, 2023
  • Construction end2 months lateforecast Jun 1, 2024

Also in Richmond