Salisbury - Polishing Pond Berm Stabilization

Salisbury, New Brunswick

completeWastewaterRNIS
Federal contribution
$331,372
Federal share60%

of $552.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
20242025
Built

Approved 22 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Ultimate recipient
Salisbury
Construction start
Jul 23, 2024(actual)
Construction end
Aug 15, 2024(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Jun 1, 2024
  • Construction end7 months earlyforecast Mar 31, 2025