Salisbury - Polishing Pond Berm Stabilization
Federal contribution
$331,372
Federal share60%
of $552.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
20242025
Built
Approved 22 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Salisbury
- Construction start
- Jul 23, 2024(actual)
- Construction end
- Aug 15, 2024(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jun 1, 2024
- Construction end7 months earlyforecast Mar 31, 2025
Also in Salisbury
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 66874 in the federal list. How to read these figures.