Culvert Replacements

Salisbury, New Brunswick

completeWastewaterCWWF
Federal contribution
$264,808
Federal share33%

of $802.9K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2017
2017201820192020
Built

Approved 5 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Salisbury
Construction start
Sep 18, 2017(actual)
Construction end
Dec 17, 2019(actual)

Against the original forecast

  • Construction end3 months earlyforecast Mar 31, 2020

Also in Salisbury

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 48232 in the federal list. How to read these figures.