2023 Sidewalk Missing Links
Federal contribution
$962,785
Federal share80%
of $1.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 2, 2024
2024
Built
Approved 11 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- County of Strathcona
- Construction start
- May 15, 2023(actual)
- Construction end
- Sep 23, 2024(actual)
Against the original forecast
- Construction end3.5 years earlyforecast Mar 31, 2028
Also in Strathcona County
- Strathcona County Transit Double Decker Buses, Fleet Refurbishment, and Cutaway Buses$4.0M
- Strathcona County Transit Regular Passenger Buses$2.6M
- Strathcona County Transit Fleet Replacement$1.8M
- Strathcona County Emerald Hills Leisure Centre Expansion Development$1.4M
- Strathcona County Millennium Place Recreation Centre - Main Floor Flooring Replacement$1.2M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67121 in the federal list. How to read these figures.