East End Moncton - Storm Sewer Detention Basin
Federal contribution
$800,000
Federal share23%
of $3.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
2024
Built
Approved 17 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Moncton
- Construction start
- Sep 5, 2023(actual)
- Construction end
- Aug 8, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast May 22, 2023
- Construction end2 months lateforecast May 31, 2024
Also in Moncton
- Moncton Infrastructure Upgrades - Ashford Development$14.6M
- Moncton - Lutz, Robinson and Westmorland Street Reconstruction$10.8M
- Tower Road Dam and Reservoir (aka Turtle Creek)$9.8M
- City of Moncton - Blue Green Algae Abatement in Potable Water System (Phase 2)$8.8M
- Storm Sewer Renewal and Improvement$8.0M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67189 in the federal list. How to read these figures.