Back to projects

Central Laundry Ventilation Upgrades

St. John's, Newfoundland and Labrador

completeVentilationCVRIS
Federal contribution
$3.4M
$3,360,000
Federal share80%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 4, 2025
202420252026
Built

Approved 23 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 15, 2023(actual)
Construction end
Mar 12, 2026(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2023
  • Construction end3 months lateforecast Dec 15, 2025

Also in St. John's