Central Laundry Ventilation Upgrades
St. John's, Newfoundland and Labrador
Federal contribution
$3.4M
$3,360,000
Federal share80%
of $4.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2025
202420252026
Built
Approved 23 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Government of Newfoundland and Labrador
- Construction start
- Jun 15, 2023(actual)
- Construction end
- Mar 12, 2026(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2023
- Construction end3 months lateforecast Dec 15, 2025
Also in St. John's