Back to projects

Mount McIntyre Recreation Centre Ventilation / Heating Upgrade

Whitehorse, Yukon

underwayVentilationCVRIS
Federal contribution
$2.1M
$2,100,000
Federal share100%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2023
today
202420252026
BuiltForecast

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
City of Whitehorse
Construction start
May 5, 2025(actual)
Construction end
Sep 16, 2026(forecast)

Against the original forecast

  • Construction start4 weeks earlyforecast Jun 1, 2025

Also in Whitehorse