Federal contribution
$5.4M
$5,414,250
Federal share75%
of $7.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 20, 2023
today
202420252026
BuiltForecast
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Whitehorse
- Construction start
- May 5, 2025(actual)
- Construction end
- Sep 30, 2026(forecast)