Storm Sewer Upgrades (Walsh River, Harrie Lake, Duley)
Labrador City, Newfoundland and Labrador
Federal contribution
$563,048
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 21, 2025
202420252026
BuiltForecast
Approved 21 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- City of Labrador City
- Construction start
- Jul 2, 2025(actual)
- Construction end
- Jun 30, 2026(forecast)
Against the original forecast
- Construction start9 months earlyforecast Mar 30, 2026
Also in Labrador City
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67330 in the federal list. How to read these figures.