Russell Heights Reconstruction
Stephenville, Newfoundland and Labrador
Federal contribution
$452,990
Federal share40%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 16, 2026
202420252026
Built
Approved 2.7 years before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Stephenville
- Construction start
- Oct 4, 2024(actual)
- Construction end
- Nov 15, 2024(actual)
Against the original forecast
- Construction start5 months lateforecast May 1, 2024
- Construction end2 weeks earlyforecast Nov 29, 2024
Also in Stephenville
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67333 in the federal list. How to read these figures.