Back to projects

Russell Heights Reconstruction

Stephenville, Newfoundland and Labrador

completeDrinking WaterGIS
Federal contribution
$452,990
Federal share40%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 16, 2026
202420252026
Built

Approved 2.7 years before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
Town of Stephenville
Construction start
Oct 4, 2024(actual)
Construction end
Nov 15, 2024(actual)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2024
  • Construction end2 weeks earlyforecast Nov 29, 2024

Also in Stephenville

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67333 in the federal list. How to read these figures.