Back to projects

Reflections Lookout

Wood Buffalo (Regional Municiaplity), Alberta

underwayActive TransportationCVRIS
Federal contribution
$1.5M
$1,528,000
Federal share80%

of $1.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 18, 2025
today
20242025202620272028
BuiltForecast

Approved 22 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 29, 2023(actual)
Construction end
Mar 31, 2028(forecast)

Against the original forecast

  • Construction start5 months lateforecast May 1, 2023

Also in Wood Buffalo (Regional Municiaplity)

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67412 in the federal list. How to read these figures.