Repair work of site and classroom doors
Federal contribution
$269,857
Federal share80%
of $337.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 4, 2024
2024
Built
Approved 16 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre de services scolaire de l'Énergie
- Construction start
- Jun 26, 2023(actual)
- Construction end
- Mar 1, 2024(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2023
- Construction end6 months earlyforecast Aug 30, 2024
Also in Shawinigan
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67423 in the federal list. How to read these figures.