Town of Rockglen - Water and Wastewater Improvements
Federal contribution
$386,062
Federal share40%
of $965.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 6, 2023
20242025
Built
Approved 5 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Rockglen
- Construction start
- Sep 5, 2023(actual)
- Construction end
- Feb 6, 2025(actual)
Against the original forecast
- Construction start5 weeks lateforecast Aug 1, 2023
- Construction end8 weeks earlyforecast Mar 31, 2025
Also in Rockglen
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67498 in the federal list. How to read these figures.