Wastewater Treatment System Rehabilitation
Federal contribution
$25,723
Federal share50%
of $51.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Rockglen
- Construction start
- Jul 27, 2017(actual)
- Construction end
- Aug 7, 2017(actual)
Against the original forecast
- Construction start4 months lateforecast Apr 1, 2017
- Construction end8 months earlyforecast Mar 31, 2018
Also in Rockglen
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50050 in the federal list. How to read these figures.