Renovation of sanitary blocks

Shawinigan, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$214,051
Federal share80%

of $267.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 4, 2024
2024
Built

Approved 16 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jun 21, 2023(actual)
Construction end
Apr 27, 2024(actual)

Against the original forecast

  • Construction start3 weeks lateforecast Jun 1, 2023
  • Construction end8 months earlyforecast Dec 31, 2024

Also in Shawinigan

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67549 in the federal list. How to read these figures.