Calgary Drop-in and Rehab Centre HVAC Replacement
Federal contribution
$2.5M
$2,499,978
Federal share80%
of $3.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedDec 12, 2024
20242025
Built
Approved 20 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Calgary Drop-in and Rehab Centre
- Construction start
- Sep 29, 2023(actual)
- Construction end
- Nov 30, 2024(actual)
Against the original forecast
- Construction end4 weeks earlyforecast Dec 31, 2024
Also in Calgary
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 67641 in the federal list. How to read these figures.